MBTA Green Line Grade Crossings

Job Highlights:

  • Grade Crossings
    10 EA
  • Track R&R New
    2850 LF
  • Rubber Grade Crossings
    482 LF
  • Bituminous Concrete
    1020 TN


Pre-Existing Concrete Panel Grade Crossings

This track and civil project typifies J. F. White Contracting Co.'s capabilities in all respects. Working through weekends during track outages, crews were assembled from multiple project sites to complete the necessary work. Several weekends were planned in advance, and each phase was managed and performed in sequence around the clock.

Coordination among our staff and crews, the MBTA, the City of Boston, emergency response agencies, suppliers and subcontractors is a J. F. White hallmark. Projects of this type leave very little room for error, and require significant on-site management to maintain schedule. Track outages are a major disruption for any transit authority, and the restoration of service is critical. J. F. White has long been known for reliability in this environment.