Granite Ridge Co-Gen Facility

Job Highlights:

  • Welding of Iso-phase Bus
  • Installed overhead 230 kv line and towers
  • Time constraints
  • Emergency mobilization

 


J. F. White’s Electrical team was contracted by Waldron Engineering, the Consulting Engineer for the Granite Ridge Co-Gen Facility in Londonderry, NH, to provide the needed work on an emergency basis.

The 500 ton, 230kv transformer needed to be reinstalled, including the welding of the new ISO-PHASE Bus and overhead 230kv line. J. F. White’s labor forces worked 24 hours a day for eight consecutive days to successfully complete this project and get the plant back on line.