Wareham Ring Bus Replacement

Job Highlights:

  • Project completed without a lost time accident.
  • No interruption to service.
  • Safety measures had to be increased due to the low clearance of the existing 69KV bus.

 

 

 

 

       

115KV Breakers

     

J.F. White was contracted to install a new 115KV Ring Bus System including it’s supporting control equipment, new low voltage panels and control cabinets. J.F. White disconnected and removed and replaced two 115KV/69KV transformers, five 115KV disconnects and three 115KV breakers were added to the system. This allowed additional capacity and versatility to the Middleboro system.

Close coordination with Middleboro Electric and National Grid was crucial to this project to maintain power with no interruption.

Contract value: $760,928